A and B can do a piece of work in 30 and 45 days respectively. They worked
together for some days, then B leaves. If B leaves 5 days before the completion of the work, how many days did they work together?​

Answers

Answered by chatnoarfan
1

Answer:

15 days

Step-by-step explanation:

Answered by dzx
0

Answer:

15 days

Step-by-step explanation:

find 1 days work of each and both together...then make an equation and solve