A and B can do a piece of work in 30 days B and C in 24 days B and C in 40 days how long will it take them to do the work together in what time can each finish it working alone
Answers
Answered by
0
Answer:
They can finish it alone as A in 40 days , B in 60 days and C in 120 days.
Answered by
19
- A and B can do a piece of work in 30 days
- B and C in 24 days
- C and A in 40 days
- Time required when all of them do the work together
- Time in which each can finish the work alone
- Let A , B , C can complete the work in A , B , C days respectively
➠
➠
➠
A and B can do the work in 30 days
➠ ------- (1)
B and C can do it in 24 days
➠ ------ (2)
C and A required 40 days
➠ ------ (3)
⟮ Adding equation (1) , (2) & (3) ⟯
➜
➜
➜
➜
➜ ------- (4)
➨ A + B + C = 20
Hence working together they can finish the work in 20 days
Now ,
From (1)
➠ ----- (5)
From (2)
➠ ------ (6)
⟮ Putting the values got from (5) & (6) to (4) ⟯
➜
➜
➜
➜
➜
➜
➜
➨ B = 40 days ------- (7)
- Hence B can finish the work alone in 40 days
⟮ Putting B = 40 from (7) to (1) ⟯
➜
➜
➜
➜
➜
➨ A = 120 days -------- (8)
- Hence A can finish the work alone in 120 days
⟮ Putting the values of A & B from (7) & (8) to (4) ⟯
➜
➜
➜
➜
➜
➜
➨ C = 60 days
- Hence C alone can finish the work in 60 days
Similar questions