A and B can do a piece of work in 30 days . If A 's work is 3/2 times of B's one day work , find how many days each can do work.​

Answers

Answered by jinadevkv
1

Answer:

A can do the work in 50 days

B can do it in 75 days

Step-by-step explanation:

suppose B does 2 parts of the work a day.

Then work done by A in a day = 2 * 3/2 = 3

Total work done by A and B in a day = 3 + 2 = 5

Therefore total work = 30 days * 5 = 150

So  time required for A to complete the work = 150 / 3 = 50 days

Time required for A to complete the work = 150 / 2 = 75 days