Math, asked by haripriyat81perpso, 1 year ago

A and B can do a piece of work in 30 days, while B and C can do the same work in 24 days and A and C in 20 days.They all work together for 10 days then B and C leave.How many days more will A take to finish the work?
​

Answers

Answered by keerthishree141
0

Answer:

74 days A will to finish the work