A and B can do a piece of work in 30 days. While B and C can do the same work in 24 days and C and A in 20 days. They all work together for 10 days when B and C leave. How many days more will A take to finish the work ?
Answers
Answered by
1
Answer:
(A + B)’s one days’ work = 1/30
(B + C)’s one days’ work = 1/24 .....(1)
(C + A)’s one days’ work = 1/20
Therefore (A + B + C)’s one days’ work
(A + B + C)’s 10 days’ work
= 10/6 = 5/8
From (1) and (2), A's one days’ work
= 1/16 – 24
= 1/48
Therefore remaining 3/8 of the work is done by A alone in 3/8 × 48
= 18 days.
Answered by
0
Answer:
Thus A will take 18 days to finish the work
Step-by-step explanation:
A+B=1/30
B+C=1/24.......(.1)
C+A=1/20
adding we get
2(A+B+C)=1/30+1/24+1/20
=1/120( 4+5+6)=15/120=1/8
So A+B+C=1/16
From (1)
A+B+C-(B+C)=1/16-1/24=1/48( 3-2)=1/48
So A=1/48.............(2)
Work done by all 3 in 10 days
=10*(A+B+C)=10*1/16=10/16=5/8
Work left=1-5/8=3/8
Thus no of days taken by A to finish the work
=(3/8) / (1/48)
=3/8*(48)
=3*6=18 days
Thus A will take 18 days to finish the work
Similar questions