Math, asked by chetu032001, 6 months ago

A and B can do a piece of work in 4 days. B and C in 6 days and C and A in 2 days. In what time A, B and C will complete the work working together ?​

Answers

Answered by aayushsharma7956
1

Answer:

3 DAYS IS REQUIRED FOR A,B,C TO DO WORK!!!

I HOPE YOU UNDERSTOOD THE QUESTION!!!