A and B can do a piece of work in 40 days,B and C in 30 days,and C and A in 24 days.How long will it take them to do the work together?A and B can do a piece of work in 40 days B and C in 30 days and C and a in 24 days how long will it take them to do the work together
Answers
Answer:
Step-by-step explanation:
Given :
A and B can do a piece of work in 40 days,
B and C can do a piece of work in 30 days &
C and A can do a piece of work in 24 days.
To find :
How long will it take them to do the work together?
Solution :
Statement 1 :
A and B can do a piece of work in 40 days.
_
⇒ Work done by A in 40 days + Work done by B in 40 days = Complete work
Let Work done by A in 1 day be "a"
Let Work done by B in 1 day be "b"
So,
⇒
⇒ ...(i)
_
Statement 2 :
B and C can do a piece of work in 30 days.
_
⇒ Work done by B in 30 days + Work done by C in 30 days = Complete work.
Let Work done by C in 1 day be "c"
So,
⇒
⇒ ...(ii)
_
Statement 3 :
C and A can do a piece of work in 24 days.
_
⇒ Work done by C in 24 days + Work done by A in 24 days = Complete work
So,
⇒
⇒ ...(iii)
_
By adding all 3 equations,.
We get,
⇒
⇒
⇒
⇒
⇒
∴ If A , B & C works for 1 day, they cn complete of the whole work,.
By multiplying both the sides by 20,
We get,
⇒
⇒
∴ It takes 20 days to complete the whole work,.
Answer: