A and B can do a piece of work in 40 days, B and C in 30 days and C and A in 24 days. in what time can each finish it working alone?
Answers
They can finish it alone as A in 40 days , B in 60 days and C in 120 days.
Step-by-step explanation:
Given : A and B can do a piece of work in 40 days, B and C in 30 days and C and A in 24 days.
To find : In what time can each finish it working alone?
Solution :
According to question,
A + B = 40 days
B + C = 30 days
C + A = 24 days
We take the LCM of 24,30 and 40
2 | 24 30 40
2 | 12 15 20
2 | 6 15 10
3 | 3 15 5
5 | 1 5 5
| 1 1 1
Their unit work in a day will be
A + B = units/day
B + C = units/day
C + A = units/day
Adding these equations ,
2A + 2B + 2C = 3+4+5
2(A + B + C) = 12
A + B + C = 6 units per day
Now, to complete 120 units they'll take a time of
Together they take A+B+C= 20 days.
So, they working alone as
For A,
A's one day work is 6-3=3 unit
A complete whole work in days
For B,
B's one day work is 6-4=2 unit
B complete whole work in days
For C,
C's one day work is 6-5=1 unit
C complete whole work in days
Therefore, they can finish it alone as A in 40 days , B in 60 days and C in 120 days.
# Learn more
A and B can do a piece of work in 30 days; B and c in 24 days ;c and A in 40 days. How long will it take them to do the work together In what time can each finish it, working alone ?
https://brainly.in/question/12464579
Answer:
i)20 days
ii) A=60 days
B=120 days
C=40 days
Step-by-step explanation:
i) (3+4+5)/120=12/120=1/10
(A+b+c+a+b+c) 1 day work =1/10
(A+B+C) =1/10×1/2=1/20
=20 days
ii) A work = 1/20-1/30
(3-2)/60 = 1/60=60 days
B work =1/20-1/24
(6-5)/120=1/120=120 days
C work=1/20-1/40
(2-1)/40=1/40=40 days