Math, asked by harshitdhir4242, 1 year ago

A and b can do a piece of work in 45 days and 40 days respectively. they beganto do the work together but a leaves after some days and then b completed theremaining work n 23 days. the number of days after which a left the work was

Answers

Answered by jasmeenj038
0

A (Aby) completes the work in 45 days &

B (Babli) completes the work in 40 days.

In a single day work completed by,

A=1/45

B=1/40

If they both work together, the work completed = 1/45+1/40=17/360

Lets assume A & B work together for ‘x’ days.

x∗17/360+23∗1/40=1 (x days both A & B are working and 23 days only B is working)

x=(1−23/40)∗360/17=17/40∗360/17=9

So after 9 days Aby left.