A and B can do a piece of work in 54 days and 48 days respectively.
They began the work together but A leaves after some days and B finishes
the remaining work in 31 days. After how many days did A leave the work?
Answers
Step-by-step explanation:
First Method:
A takes 54 days of work.
B takes 48 days of work.
LCM = (54, 48) = 432/48 = 9
Efficiency of A = 432/54 = 8
Efficiency of B = 432/48 = 9
B finishes remaining work on 31 days
i. e, 31 × 9 = 279 work is done by B.
Remaining work is 432 - 279 = 153
153 work is done by A and B.
They take 153/17 days (9 + 8 =17) efficiency.
They take 9 days to work together.
So, A leave after 9 days
Second Method:
A can do work in 54 days.
So, in one day A does (1/54) part of work.
B does (1/48) part of work.
So together, in one day they do ((1/54)+(1/48)) part of work.
Now, B does 1/48 part of work in one day. So, in 31 days B will do 31/48 part of work.
Remaining work: (1-31/48) = 17/48 part.
(17/48) part has been done by both A and B
initially.
Now,
A & B together do ((1/54)+(1/48)) part of work in 1 day
So, 17/48 part will be done in = (17/480/((1/54)+ (1/48)) days = 9 days
So, after 9 days A left the work.
Third Method:
Total work to be done LCM(54,48)=432 parts
So A does 432 parts in 54 days so A does 432/5458 parts/day
Similarly B does 9 parts/day
Together they do 17 parts/day
Let they work together for d days after which A left
So they do 17xd parts
Now B does remaining work in 31 days
So 17xd +31x9= 432
d = 9
So A left after 9 days