Math, asked by ManoramaUQ, 1 year ago

A and B can do a piece of work in 6 daya and 4 days respectively.A started the work ,worked at it for 2 days and then was joned by B.Find the total time taken to complete the work.

Answers

Answered by expertjinesh1507
4
1 day work of a=1/6
1 day work of b=1/4
1 day work of a and b=5/12
2 day work of a=1/3
work left = 2/3
a and b can finish it in = 2/3รท5/12
=8/5 days
total time taken = 2+8/5
=18/5 days
=3.6 days
Answered by bikpin
5
is this helpful for u if any questions please feel free .
Attachments:

bikpin: add 2 in the answer
bikpin: by mistake i forget
bikpin: sorry
bikpin: answer is 1.6+2=3.6
ManoramaUQ: okay
Similar questions