Math, asked by seemalodhi826, 5 months ago

A and B can do a piece of work in 6 days and 4 days respectively. A started the work; worked at it for 2 days and then was joined by B. Find the total time taken to complete the work

Answers

Answered by EliteZeal
21

\huge{\blue{\bold{\underline{\underline{Answer :}}}}}

 \:\:

 \large{\green{\underline \bold{\tt{Given :-}}}}

 \:\:

  • A and B can do a piece of work in 6 days and 4 days respectively

 \:\:

  • A started the work 2 days earlier than B

 \:\:

 \large{\red{\underline \bold{\tt{To \: Find :-}}}}

 \:\:

  • Total time taken to complete the work

 \:\:

\large{\orange{\underline{\tt{Solution :-}}}}

 \:\:

  • Let the total time taken to complete the work be "x"

 \:\:

 \underline{\bold{\texttt{A's one day work :}}}

 \:\:

 \sf \dfrac { 1 } { 6 }

 \:\:

 \underline{\bold{\texttt{B's one day work :}}}

 \:\:

 \sf \dfrac { 1 } { 4 }

 \:\:

As "A" started the work alone from the first day thus "A" will work for "x" days to complete the work.

 \:\:

As "B" started the work 2 days after "A" thus "B" will work for "x - 2" days to complete the work.

 \:\:

 \underline{\bold{\texttt{A's work in x days :}}}

 \:\:

 \sf x \times \dfrac { 1 } { 6 }

 \:\:

 \underline{\bold{\texttt{B's work in (x - 2) days :}}}

 \:\:

 \sf (x - 2) \times \dfrac { 1 } { 4 }

 \:\:

As we assumed that they will complete the work in x days while counting from the very first day.

 \:\:

So,

 \:\:

 \sf x \times \dfrac { 1 } { 6 } + (x - 2) \times \dfrac { 1 } { 4 } = 1

 \:\:

 \sf \dfrac { x } { 6 } + \dfrac { x - 2 } { 4 } = 1

 \:\:

 \sf \dfrac { 2x + 3x - 6 } { 12 } = 1

 \:\:

 \sf \dfrac { 5x - 6 } { 12 } = 1

 \:\:

➜ 5x - 6 = 12

 \:\:

➜ 5x = 12 + 6

 \:\:

➜ 5x = 18

 \:\:

➨ x = 3.6 days

 \:\:

  • Hence A & B together can finish the work in 3.6 days
Answered by satyamdraugscpr
0

Answer:

X=3.6 days this is answered

Similar questions