A and B can do a piece of work in 6 days and 4 days respectively. A started the work; worked at it for 2 days and then was joined by B. Find the total time taken to complete the work
Answers
Answered by
21
- A and B can do a piece of work in 6 days and 4 days respectively
- A started the work 2 days earlier than B
- Total time taken to complete the work
- Let the total time taken to complete the work be "x"
➠
➠
As "A" started the work alone from the first day thus "A" will work for "x" days to complete the work.
As "B" started the work 2 days after "A" thus "B" will work for "x - 2" days to complete the work.
➠
➠
As we assumed that they will complete the work in x days while counting from the very first day.
So,
➜
➜
➜
➜
➜ 5x - 6 = 12
➜ 5x = 12 + 6
➜ 5x = 18
➨ x = 3.6 days
- Hence A & B together can finish the work in 3.6 days
Answered by
0
Answer:
X=3.6 days this is answered
Similar questions
Math,
2 months ago
Physics,
2 months ago
Social Sciences,
2 months ago
Hindi,
5 months ago
Social Sciences,
5 months ago
Computer Science,
10 months ago
Math,
10 months ago