A and B can do a piece of work in 72dayss B, And C can do it in 120 days and A and C can do it in 90 days when A, B and C work together, how much work is finished by them in 3 days
Answers
Answered by
0
Answer:
(A and B)'s 1 days work = 1/72.
(B and C)'s 1 days work = 1/120. (C and A)'s 1 days work = 1/90.
By adding we get,
2(A+B+C)'s 1 days work=2(1/72+1/120+1/90)
LCM of 72,120,90= 360
5+3+4 by 360
= 12 by 360
therefore ;(12/360)
=1 by 30 or 1/30
= 1/30 multiply by 1/2= 1/60
(A+B+C)'s 1 days work if they do it together=60
tHerefore;
(A+B+C)'s 3 days work is 60 mulitiply by 3= 120 days.
So, your answer is 120 days.