A and B can do a piece of work in 8 days,B and C can do the same work in 12 days and A and c complete it in 8 days .In how many days A,B and C can complete the whole work ,working together
Answers
Answered by
0
When A and B can do a piece of work in 8 days,B and C can do the same work in 12 days and A and C complete it in 8 days .A,B and C can complete the work in 6 days.