A and B can do a piece of work in
9 days. A can do it in 18 day. B will
do the same work alone in
Answers
Answered by
0
Answer:
A = 9days
work done in 1 day = 1/18 0f work
time taken by A and B = 9 days
so work done in 1 day =1/9 of work
work done in one day by A + work done in one day by B = work done by both
1/18 + B work of day = 1/9 work
B work of day = 1/9-1/18
= 1/9
so time taken by B is 9 days..
hope it helps you