A and B can do a piece of work is 6 days, while working
Separately B takes 5 days more than A. How long
would each take to do it alone.
Answers
Answered by
5
Answer:
A+B's 1 day work=1/6
B's 1 day work=1/6+1/5
=11/30
A's 1 day work=1/6-11/30
=6/30
=3/15
=1/5
A's work=5days
B's work=5+5
=10 days
pls follow me
mark my ans the brainliest
Similar questions