Math, asked by Dhanush7969, 1 year ago

A and b can do a work in 18 and 24 days respectively. they worked together for 8 days and then a left. the remaining work was finished by b in.

Answers

Answered by Muskan1101
24
Solution:-
A can do piece of work in 18 days
One day work of A is 1/18
B can do the piece of work in 24 days
One day work of B =1/24
So,
(A+B)'s one day work=
 =  >  \frac{1}{18}  +  \frac{1}{24}
 =  >  \frac{4 + 3}{72}  \\  =  >  \frac{7}{72}
They worked for 8 days
So,
Worked complete =
 =  >  \frac{7}{72}  \times 8 \\  =  >  \frac{7}{9}
Now,
Remain work=
 =  > 1 -  \frac{7}{9}  \\  =  >  \frac{2}{9}
So,
the remain work done by B in
 =  >  \frac{2}{9}  \div  \frac{1}{24}  \\  =  >  \frac{2}{9}  \times  \frac{24}{1} \\  =  >  \frac{16}{3}
So,the remain work done by B in 16/3 days
Answered by aquialaska
6

Answer:

In   \frac{16}{3} days B finish the work left by A.

Step-by-step explanation:

No of days A took to complete work = 18 days

Work Done by A in a day = \frac{1}{18}

No of days A took to complete work = 24 days

Work Done by A in a day = \frac{1}{24}

So,

Work done by A and B both together in a day = \frac{1}{18}+\frac{1}{24}=\frac{7}{72}

Work done by A and B both together in 8 day = 8\times\frac{7}{72}=\frac{7}{9}

Remaining work = 1-\frac{7}{9}=\frac{2}{9}

So, No of days taken by B to do remaining work = \frac{2}{9}\times24=\frac{16}{3}

Therefore, In   \frac{16}{3} days B finish the work left by A.

Similar questions