A and b can do a work in 18 and 24 days respectively. they worked together for 8 days and then a left. the remaining work was finished by b in.
Answers
Answered by
24
Solution:-
A can do piece of work in 18 days
One day work of A is 1/18
B can do the piece of work in 24 days
One day work of B =1/24
So,
(A+B)'s one day work=
They worked for 8 days
So,
Worked complete =
Now,
Remain work=
So,
the remain work done by B in
So,the remain work done by B in 16/3 days
A can do piece of work in 18 days
One day work of A is 1/18
B can do the piece of work in 24 days
One day work of B =1/24
So,
(A+B)'s one day work=
They worked for 8 days
So,
Worked complete =
Now,
Remain work=
So,
the remain work done by B in
So,the remain work done by B in 16/3 days
Answered by
6
Answer:
In days B finish the work left by A.
Step-by-step explanation:
No of days A took to complete work = 18 days
Work Done by A in a day =
No of days A took to complete work = 24 days
Work Done by A in a day =
So,
Work done by A and B both together in a day =
Work done by A and B both together in 8 day =
Remaining work =
So, No of days taken by B to do remaining work =
Therefore, In days B finish the work left by A.
Similar questions