A and B can do a work in 20 days. B and C can do it in 30 days. A worked on it for 10 days and B worked on it for 15 days. C finished the remaining work in 17 days. How many days would it have taken for C to complete the entire work all alone?
Answers
ANSWER
______________________________________
If A and B take 20days to complete a work they will complete 1
20 of the work in a day
so,
=> A + B = 1/20
like,
=> B + C = 1/30
like, => 10A + 15B + 17C = 1
=> 10A + 10B + 5B + 5C + 12C = 1
=> 10( 1 ) 5( 1 ) + 12C = 1
20 30
=> 12C = 1 - 1 - 1 = 12 - 6 - 2 = ( 12 - 6 -2 )/12
2 6 12 12 12
= 4 = 1
12 3
hence,
=> C= 1 Units per day.
36
: It takes 36 days to complete the work alone.
______________________________________
36 days.
______________________
A and B can do a work in 20 days.
So, A and B done of the work in one day.
A + B = _______(1)
Similarly, B and C can do it in 30 days.
So, B and C done of the work in one day.
B + C = done _______(2)
According to question,
10A + 15B + 17C = 1
10A + 10B + 5B + 5C + 12C = 1
Taking 10 and 5 as common,
10(A+B) + 5(B+C) + 12C = 1______(3)
Put the value of eq (1) and (2) in eq (3) :
10 ( ) + 5 ( ) + 12C = 1
+ + 12C = 1
12C = 1 - -
12C =
12C =
C =
C =
It takes 36 days for C to complete the entire work all alone.