A and B can do it piece of work in 14 days and 21 days respectively. They start work together but 3days before completely work A leave it. In How many days work will be finish?
SreekanthK:
Put my answer as best
Answers
Answered by
2
Suppose A & B together could do work in n days, (n = 8.4).
A left after n-3 days, ie., 5.4 days.
Work left by A is 3/14.
B can do that in 4.5 days.
Total Time is n-3 days + 4.5 = 12.9.
A left after n-3 days, ie., 5.4 days.
Work left by A is 3/14.
B can do that in 4.5 days.
Total Time is n-3 days + 4.5 = 12.9.
Answered by
2
In 1 day (A+B) can do work = 1/14 + 1/21 = 5/42
Now, 3 days before Completion the work remaining is = 3 days work = 3 * 5/42 = 5 / 14. This is the work remained when A left the project.
So 1 - 5/14 = 9/ 14 work was done by A & B together. The time taken for that would be : (9/14) / (5/42) = 27 / 5 days = 5.4 days
Now the remaining work 5/14 is done by B alone.
1 day work by B = 1/21
B took (5 /14) / (1/21) = 15/2 = 7.5 days
Total time to complete project is 5.4 + 7.5 = 12.9 days
Now, 3 days before Completion the work remaining is = 3 days work = 3 * 5/42 = 5 / 14. This is the work remained when A left the project.
So 1 - 5/14 = 9/ 14 work was done by A & B together. The time taken for that would be : (9/14) / (5/42) = 27 / 5 days = 5.4 days
Now the remaining work 5/14 is done by B alone.
1 day work by B = 1/21
B took (5 /14) / (1/21) = 15/2 = 7.5 days
Total time to complete project is 5.4 + 7.5 = 12.9 days
Similar questions