Math, asked by NehaChocoholic2162, 1 day ago

A and B can finish a peice of work in 16 days and 12 days respectively. A started the work amd worked at it for 2 days . he then was joined by B. find the total time taken to finish the work

Answers

Answered by kavitaarjun1990
0

Answer:

Solution

verified

Verified by Toppr

Step 1: Evaluate the word problems on time and work.

Given,

A and B can finish a piece of work in 16 days and 12 days respectively.

Work done by A in one day=

16

1

Work done by B in one day=

12

1

Work done by A in 2 days=2×

16

1

=

8

1

Let A and B worked together for x days to complete the remaining work.

8

1

+x(

16

1

+

12

1

)=1

⇒x×

48

7

=

8

7

⇒x=6

Hence, the total time taken to finish the work is (2 + 6) days = 8 days