A and B can finish a piece of work in 15 days,B and C in 20 days while C and A in 30 days.How long will each take to finish the work?​

Answers

Answered by vermaramjanam09
1

Answer:

A+B can do a piece of work in 15 days

work done by A and B in 1days =1/15 part of work

B+C can done a work in 20

work done by B and C in 1days =1/20

C+A can do a work in 30 days

work done by C and A in 1 day =1/30

2(a+b+c)

2(1/15+1/20+1/30)

=22/60

so a+ b+c can do work in 60/22 days