A and B can finish a piece of work in 16 days and 12 days respectively a started the work and worked at it for 2 days. then join by B. find the total time taken to finish the work.
Answers
⭐ A and B can finish a piece of work in 16 days and 12 days respectively a started the work and worked at it for 2 days. then join by B. find the total time taken to finish the work.
✒ The total time taken to finish the work is 8 days.
Let whole work be W.
⇒ Work done by A in one day = w/16
Work is done by B in one day = w/12
⇒ A worked for 2 days =2× w/16
= w/8
A and B worked for x days ( let )
⇒ w/8 + x(w/16 + w/12)
⇒ x × 7/48 =7/8
⇒ x = 7/8×48/7
⇒x = 48/8
⇒x=6 days.
If A and B work together they finish the remaining work in 6 days
ATQ,
A worked alone 2 day
So total work = A + A & B
=> 6+2= 8 days
✌ Sᝪ Tᕼᗴ TᝪᎢᗩᏞ ᎢᏆᗰᗴ ᎢᗩᏦᗴᑎ Ꮖᔑ 8 ᗞᗩᎩᔑ.
________________________________
Given:-
A can finish his work in 16 days
•1 day work of A = 1/16
B can find the piece of work in 12 days
• 1 day work of B = 1/12
To find :-
◆ We have to find how much time taken by both A and B to finish the work
Now ,
- So , A alone can do work for two days then B joined !
- Find the two day work of A
- Extra work done by A compare to B
1 day work of A = 1/16
2 days = 2×1/16= 1/8
- Remaining work ?
- Let total work = 1
- Now caluculate the time taken by both to finish the given work !
One day work of A and B
If A and B work together they finish work in 48/7 days
Now find how much time they both take to finish the remaining work
If A and B work together they finish the remaining work in 6 days and It is given that A do 2 days Alone
So total work is calucuted by 2 days Alone work of A + Remaining work done by A and B together
=> 6+2= 8 days