Math, asked by singhbarun391, 9 months ago

A and B can finish a piece of work in 16 days and 12 days respectively a started the work and worked at it for 2 days. then join by B. find the total time taken to finish the work.​


singhbarun391: anyone know the answer

Answers

Answered by Anonymous
34

\mathcal{\huge{\fbox{\fbox{\red{Question:-}}}}}

⭐ A and B can finish a piece of work in 16 days and 12 days respectively a started the work and worked at it for 2 days. then join by B. find the total time taken to finish the work.

\mathcal{\huge{\underline{\underline{\green{Answer:-}}}}}

The total time taken to finish the work is 8 days.

\mathfrak{\huge{\underline{\underline{\orange{Solution:-}}}}}

Let whole work be W.

⇒ Work done by A in one day = w/16

Work is done by B in one day = w/12

⇒ A worked for 2 days =2× w/16

= w/8

A and B worked for x days ( let )

⇒ w/8 + x(w/16 + w/12)

⇒ x × 7/48 =7/8

⇒ x = 7/8×48/7

⇒x = 48/8

⇒x=6 days.

If A and B work together they finish the remaining work in 6 days

ATQ,

A worked alone 2 day

So total work = A + A & B

=> 6+2= 8 days

Sᝪ Tᕼᗴ TᝪᎢᗩᏞ ᎢᏆᗰᗴ ᎢᗩᏦᗴᑎ Ꮖᔑ 8 ᗞᗩᎩᔑ.

________________________________


Anonymous: thank you
singhbarun391: how can I make you brainlist
Anonymous: after sometime
singhbarun391: ok
Anonymous: hn
Brâiñlynêha: Mistakes in answer ! correct it
Anonymous: ok
kailashmeena123rm: Gute Arbeit
Anonymous: Equate the expession W/8 + x( W/16 + W/12 ) to ' W ' as u assumed whole work donne as 'W'
kailashmeena123rm: yes
Answered by Brâiñlynêha
42

Given:-

A can finish his work in 16 days

•1 day work of A = 1/16

B can find the piece of work in 12 days

• 1 day work of B = 1/12

To find :-

◆ We have to find how much time taken by both A and B to finish the work

Now ,

  • So , A alone can do work for two days then B joined !

  • Find the two day work of A

  • Extra work done by A compare to B

1 day work of A = 1/16

2 days = 2×1/16= 1/8

  • Remaining work ?

  • Let total work = 1

  • \sf 1- \dfrac{1}{8} =\dfrac{8-1}{8} =\dfrac{7}{8}

  • Now caluculate the time taken by both to finish the given work !

One day work of A and B

\longrightarrow\sf 1 \ day\ work \ of \ (A+B)= \dfrac{1}{16}+\dfrac{1}{12}\\ \\ \longrightarrow\sf \dfrac{3+4}{48}\\ \\ \longrightarrow\sf \dfrac{7}{48}\\ \\ \longrightarrow \sf A+B= \dfrac{48}{7}\ days

If A and B work together they finish work in 48/7 days

Now find how much time they both take to finish the remaining work

\longrightarrow\sf Time = \dfrac{\cancel7}{\cancel8}\times \dfrac{\cancel{48}}{\cancel7} \\ \\ \longrightarrow\sf  6 days

If A and B work together they finish the remaining work in 6 days and It is given that A do 2 days Alone

So total work is calucuted by 2 days Alone work of A + Remaining work done by A and B together

=> 6+2= 8 days

\bigstar{\boxed{\sf{ Total \ time \ taken\ (A+B) =8 days }}}


Anonymous: Perfect!
Brâiñlynêha: Thank you ( ・ิϖ・ิ)
MOSFET01: Good
Brâiñlynêha: Thanka
kailashmeena123rm: Gute Arbeit
Similar questions