Math, asked by karma565, 1 year ago

A and b can finish a piece of work in 16 days and 12 days respectively. a started the work and worked at it for 2 days. he was then joined by
b. find the total taken to finish the work

Answers

Answered by shivam316
3
Required answer is 6.total time taken by them is (6+2)=8 days