A and B can finish a piece of work in 16 days and 12 days respectively. A started the work and worked at it for 2 days. He was then joined by B. Find the total time taken to finish the. work.
Nikhil011:
the ans of this question is 8 days but how is it find...
Answers
Answered by
8
Do it LCM METHOD.
A= 16 D
B = 12 D
SO LCM OF 12 AND 16 IS 48. SO THAKE THE WHOLE WORK AS 48 UNITS.
NOW.
A CAN 3 Units / day and B can 4 units / day.
A started the work and works for 2 day so . 6 units WORK IS DONE. SO REST WORK IS 48-6= 42 UNITS. NOW A AND B BOTH COMPLIT THE WORK. SO 1 DAY WORK OF A AND B IS 3+4= 7 UNITS. SO TIME IS NEED = 42/7= 6 DAY.
SO TOTAL DAY TO COMPLITE THE WORK IS = 6+2 DAY = 8 DAY. IT IS LCM METHOD. IF U DONT UNDERSTAND THEN MESSAGE ME. I WILL DO IT OTHER METHOD. IF THIS METHOD IS HELFFUL. THEN MARK AS BARINLIST PLEASE
A= 16 D
B = 12 D
SO LCM OF 12 AND 16 IS 48. SO THAKE THE WHOLE WORK AS 48 UNITS.
NOW.
A CAN 3 Units / day and B can 4 units / day.
A started the work and works for 2 day so . 6 units WORK IS DONE. SO REST WORK IS 48-6= 42 UNITS. NOW A AND B BOTH COMPLIT THE WORK. SO 1 DAY WORK OF A AND B IS 3+4= 7 UNITS. SO TIME IS NEED = 42/7= 6 DAY.
SO TOTAL DAY TO COMPLITE THE WORK IS = 6+2 DAY = 8 DAY. IT IS LCM METHOD. IF U DONT UNDERSTAND THEN MESSAGE ME. I WILL DO IT OTHER METHOD. IF THIS METHOD IS HELFFUL. THEN MARK AS BARINLIST PLEASE
Answered by
54
For average work we have to find the LCM.
SO,
For A,
Work done in one day =48/16 =3
For B,
Work done in one day = 48/12 = 4
According to the question,
A has done work for 2 days
so, 2×3 = 6
Remaining days = 46 (because A has done work for 2 days.)
A+B can do 7 works together (4+3 =7 )
Therefore , 42 / 7 = 6
(48-6 =42)
Similar questions