Math, asked by riya8848, 1 month ago

A and B can finish a piece of work in 16 days and 12 days respectively. A started the work abd worked ai it for 2 days. He was then joined by B. Find the total time taken to finish the work.​

Answers

Answered by sreenidhi3124
1

Answer:

6 days

Step-by-step explanation:

Let whole work be W.

⇒ Work done by A in one day =

16

W

Work is done by B in one day =

12

W

⇒ A worked for 2 days =2×

16

W

=

8

W

A and B worked for x days ( let )

8

W

+x(

16

W

+

12

W

)=W

⇒x×

48

7

=

8

7

⇒x=6 days.

Hence, the answer is 6 days.