Math, asked by PravinParmar6673, 10 months ago

A and B can finish a piece of work in 16days and 12 days respectively A started the work and worked at it for 2 days. He was then joined by B. find the total time taken to finish the work

Answers

Answered by muhammadarif70
2

Answer:

total time taken = 2 days by A alone + 6 days by both Aand B = 8 days

Step-by-step explanation:

A finishes the work in 16 days.

A finishes 1/16 of the work in one day.

A had worked for two days= 2*1/16 = 1/8

the work left after A has worked for two days = 1- 1/8 = 7/8

B finihses the work in 12 days

in 1 day B finishes 1/12 of the work.

A and B togeher in one day can finish= 1/16+1/12 = (3+4)/48= 7/48 of work

A and B together can complete the remaining work= (7/8) / (7/48)= 7*48/8*7 = 6 days.

therefore total time taken = 2 days by A alone + 6 days by both Aand B = 8 days

Stay Blessed ❤

Similar questions