Math, asked by banditapattnaik, 9 months ago

A and B can finish a piece of work in 6 days and 4 days respectively. A started the work, and after 2 days, B also joined the work. Find the total time taken by both of them to finish the work.

(Explain the procedure and solve using unitary method; No spam; 16 points)​

Answers

Answered by rohithreddy2001
0

Answer:

18/5 days

Step-by-step explanation:

Hi,

Given that A can finish a piece of work in 6 days,

So, in one day A will do 1/6 th of work,

Given that B can finish a piece of work in 4 days,

So, in one day B will do 1/4 th of work,

Given that initially A has worked for 2 days,

So A will complete 2*1/6 = 1/3 rd of work

Remaining Work = 2/3 rd of work.

If A and B works together,

In 1 day, bot A and B could do = (1/6 + 1/4) of work

= 5/12 th of work

So, 2/3 rd of work requires 2/3*1/(5/12)

= 8/5 days,

Total time , to finish the work

= Time A working alone an Time taken when both A and B are

working together

= 2 + 8/5

= 18/5 days

Hope, it helps !

please mark it as brainliest.

Answered by madhokyash75
0

Brainly.in

What is your question?

madhokyash75

paglu1 avatar

paglu1

03

A and B can finish a piece of work in 6 days and 4 days respectively. A started the work and worked for 2 days. He was then joined by B. Find the total time taken to finish the work.

SEE ANSWERS

Answers

Brainly.in

What is your question?

madhokyash75

paglu1 avatar

paglu1

03.03.2018

Math

Secondary School

+5 pts

Answered

A and B can finish a piece of work in 6 days and 4 days respectively. A started the work and worked for 2 days. He was then joined by B. Find the total time taken to finish the work.

2

SEE ANSWERS

Answers

Lakshya20041

Lakshya20041Helping Hand

I hope it will help you

Click to let others know, how helpful is it

4.0

128 votes

THANKS 184

Report

paglu1

thanks very much friemd

paglu1

I'll never forget what you have done for me....

paglu1

thanks once again

Lakshya20041

it's ok

Lakshya20041

that's my pleasure

VEDULAKRISHNACHAITAN

VEDULAKRISHNACHAITANSamaritan

Answer:

18/5 days

Step-by-step explanation:

Hi,

Given that A can finish a piece of work in 6 days,

So, in one day A will do 1/6 th of work,

Given that B can finish a piece of work in 4 days,

So, in one day B will do 1/4 th of work,

Given that initially A has worked for 2 days,

So A will complete 2*1/6 = 1/3 rd of work

Remaining Work = 2/3 rd of work.

If A and B works together,

In 1 day, bot A and B could do = (1/6 + 1/4) of work

= 5/12 th of work

So, 2/3 rd of work requires 2/3*1/(5/12)

= 8/5 days,

Total time , to finish the work

= Time A working alone an Time taken when both A and B are

working together

= 2 + 8/5

= 18/5 days

Hope, it helps !

Similar questions