A and B can finish a piece work in 16 days and 12 days respectively. A started the work and worked at it for 2 days . He was then joined by B . Find the total time taken to finish the work

Answers

Answered by Umeshlohani
1

total 8 days taken will be 8 days

see explanation in attachment

Attachments:
Answered by mr519ha80
2

Answer:

Step-by-step explanation: