A and B can finish a work in 10 days A alone can do it in 30 days . The number of days which B alone can do that work is
Answers
Answered by
1
Answer:
Hence, B, alone can complete the work in 15 days.
Hopefully it helps you, army. Nice to meet you and answer to your questions.
Answered by
0
Answer:
Hope I help you Army
Step-by-step explanation:
(A+B)’s 1 day’s work =
A’s 1 day’s work =
∴ B’s 1 day’s work =
=
Hence, B, alone can complete the work in 15 days.