A and B can finish a work in 10 days A alone can do it in 30 days . The number of days which B alone can do that work is​

Answers

Answered by goutamsinha2012
1

Answer:

Hence, B, alone can complete the work in 15 days.

Hopefully it helps you, army. Nice to meet you and answer to your questions.

Answered by gowtampal
0

Answer:

Hope I help you Army

Step-by-step explanation:

(A+B)’s 1 day’s work = 

A’s 1 day’s work = 

∴ B’s 1 day’s work = 

=

Hence, B, alone can complete the work in 15 days.