A and b can finish a work in 10 days and 15 days a work on it for 5days how much time it will take to finish work
Answers
Answered by
0
work done by A = 1/10
work done by B = 1/15
work done. by a and b = 1/10 + 1/15
= 1/6
work done in 5 days = 1/5×10
=2
remaining work = 2-1/6
13/6 days
work done by B = 1/15
work done. by a and b = 1/10 + 1/15
= 1/6
work done in 5 days = 1/5×10
=2
remaining work = 2-1/6
13/6 days