A and B can finish a work in 10 days while B and C can do it in 18 days. A started the work, worked for 5 days, then B worked for 10 days and the remaining work was finished by C in 15 days. In how many days could C alone have finished the whole work?

Answers

Answered by XDPrEm
1

Answer:

45 Days

Step-by-step explanation:

Let 'C' complete the work in x days.

Work done by (A + B) in 1 day =

110 work

Work done by (B + C) in 1 day =

118 work

A's 5 day's work + B's 10 day's work + C's 15 day's work

= 1

510+518+10x = 1

=> x = 45 days.