Math, asked by mamtarana3406, 11 months ago

A and B can finish a work in 15 days, B and C in 20 days,
while C and Ain 30 days, then A alone can finish the work
in :​

Answers

Answered by sayadnasim786
1

Answer:

40 days

Step-by-step explanation: