A and B can finish a work in 18 days but time taken by A if he works alone is 18+p and B working alone take 18+ q days also p:q=9:4 what will be the efficiency of A and B
Answers
Answered by
1
Answer:
A alone can finish a work in 45 days
B alone can finish a work in 30 days
Step-by-step explanation:
Given:
A can finish a work = (18+p) days
B can finish a work = (18+q) days
A's 1 day work
B's 1 day work
(A+B)'s 1 day work
But, as per given data,
(A+B)'s 1 day work
.........(1)
Also, p:q = 9:4
put p=27 in (1) we get
A alone can finish a work in 18+27 = 45 days
B alone can finish a work in 18+12 = 30 days
Similar questions