A and B can finish a work in 2 Hours 24 minutes if a alone can finish the work in 4 hours how long will be take to finish the work alone
Answers
Answered by
2
Step-by-step explanation:
as a and b together can do in 144 min and a alone can do in 240 min
using formula : xy/(x+y) =144 where x=240 and we need to calculate for y
solving we get you= 30 min or 1/2 hour