A and B can finish a work in 24 days and 30 days respectively. if they work on alternate days, starting with B , then in how many days the work will be completed?
Answers
Answered by
0
Answer:
okokokookokk
Step-by-step explanation:
please mark me as brainlist answer
Answered by
0
20
Step-by-step explanation:
a=24
b=30