A and B can finish a work in 30 days. They
worked for it for 20 days and then B left. The
remaining work was done by A alone in 20 more
days. A alone can finish the work in
(a) 54 days
(b) 60 days
(c) 48 days
(d) 50 days
Answers
Answered by
9
:
(b) 60 days
Step by step explanation:
Amount of work done in 1 day = 1/30
Amount of work done in 20 days =20×1/30= 2/3
Remaining work = 1-2/3= 1/3
Given :
A completes 1/3 work in 20 days
Therefore, A can finish the whole work in (20×3)= 60 days.
HOPE THIS HELPS U
MARK ME AS BRAINLIEST AND FOLLOW ME
THANK YOU