A and b can finish a work, working on alternative days, in 17 days, where a works on the first day. similarly they can finish the work, working on alternate days, in 53/3 days, where b works on the first day. c, working alone, can complete the work in 35 days. in how many days can the work be completed when a, b, and c work together?
Answers
Answered by
14
22 days will be taken to complete the work
Answered by
4
Answer:
33 days
Step-by-step explanation:
Sine , given in the question is A and B can finish a work, working on alternative days,
17 days would be required when A works first day;
53/3 days would be required when B works first day;
So, the total days required when A and B works together would be 53/3-17
= 2 days
So, the work can be completed in 2 daus when A and B works together everyday;
Now , as per the question, C can finish the work in alone in 35 days.
So, the number of days required to complete the work given that A , B , C work together is 35 - 2
= 33 days;
So, the total days would be 33 days when A , B , C works togetherly.