A and B can finish work in 4 days while A alone can do in 6 days. The number of days B will take to complete work is?
Answers
Answered by
40
HERE'S THE ANSWER .
______________________________
♠️
⏺️ ___ ( 1 )
♠️
⏺️ ___( 2 )
▶️ On ( 1 ) - ( 2 )
=>
⏺️ L.C.M. = 12
=>
=>
♠️ So B will alone complete work in 12 days
HOPE HELPED...
:)
hm0002716:
Thanks Dude....
Answered by
38
ATQ
#A + B = 1 / 4 ....1
# A = 1 / 6 ........2
B = ?
now , 1 - 2
B = 1 / 4 - 1 / 6
B = 3-2 / 12
B = 1 / 12
So B complete work in 12 days
✌️
#A + B = 1 / 4 ....1
# A = 1 / 6 ........2
B = ?
now , 1 - 2
B = 1 / 4 - 1 / 6
B = 3-2 / 12
B = 1 / 12
So B complete work in 12 days
✌️