Math, asked by manojkumar125042, 2 months ago

A and B can finish work in 6 days and 4 days respectively. A started the work and worked at in for 2 days . He was joined by B . find the total time taken to finish the work​

Answers

Answered by shivanikansal
1

Step-by-step explanation:

total time taken to finish the work is 3 3/5 days

Attachments:
Similar questions