A and B can paint the fence of a park in 8 days, B and C can paint the fence in 12 da
C and A can paint the fence in 6 days. In how many days will (i) each one of the
the fence, (ii) all of them working together paint the fence?
Answers
Answered by
12
Answer:
A+B one day work=1/8
B+C one day work= 1/12
C+A one day work= 1/6
adding all equation
2(A+B+C) one day work= 1/8+1/12+1/6
= 3+2+4/24
=9/24
A+B+C one day work=9/24*2=9/48
= 3/16
A+B+C complete work in 16/3days
A one day work = A+B+C one day work- B+C one day work
A one day work = 3/16 -1/12=9-4/48
=5/48
A complete work in 48/5
similarly
B one day work =3/16 -1/6=9-8/48
=1/48
B complete work in 48 days
similarly
C one day work =3/16 -1/8
C one day work =3-2/16=1/16
C complete work in 16 days