A and B can polish the floors of a building in 20 days .A alone can do 1/4 of this work in 15days .In how many days can B alone polish the floor of the building.
Answers
Answered by
13
Answer:
30 Days
Step-by-step explanation:
A+B can do in 20 days
A can do 1/4 in 15 days
so A can do whole work in 15*4 = 60 days
1/B = 1/(A+B) - 1/A
1/B = 1/20 - 1/60
1/B = (1/60)(3-1)
1/B = 2/60
B = 30 Days