Math, asked by PinkCandy, 1 day ago

A and B can polish the floors of a building in 25 days. A alone can do 1/3 of this job in 15 days. In how many days can B alone polish the floors of the building?

Answers

Answered by Dalfon
33

Answer:

56 days

Step-by-step explanation:

Given that A and B can polish the floors of a building in 25 days. A alone can do 1/3 of this job in 15 days.

We need to find out that how many days can B alone polish the floors of the building.

Let's say that B complete his work in x days and 1/x of the work in 1 day.

Now,

A and B polish the floor in 25 days.

In 1 day = 1/25 of the work = 0.04 of the work

A alone can do 1/3 of the job in 15 days.

1 day = 1/3 × 1/15 = 1/45 = 0.022 of the work

Therefore,

Total work done by A + B in one day = 1/25

→ 1/x + 0.022 = 0.04

→ 1/x = 0.04 - 0.022

→ 1/x = 0.018

→ x = 1/0.018

→ x = 55.56

→ x = 56 (approx.)

Therefore, B alone can polish the floor in 56 days.

Answered by itsmefahad
0

Answer:

56 days

is a correct answer in this question