A and B can together complete a piece of work in 6 days. If A work alone for 2 days and completes 1/4 thof the work,
In how many days can B alone complete the rest of work
(a 24 days
(b) 16 days
(c) 20 days
d 18 days
Answers
Step-by-step explanation:
if A worked alone he can complete 1/4 in 2 days therefore whole work in 8 days
thus 1/8+1/B=1/6
1/B = 1/6-1/8
1/B=8-6/48
1/B=2/48
1/B=1/24
B=24
Answer:
A worked alone he can complete 1/4 in 2 days therefore whole work in 8 days
thus 1/8+1/B=1/6
1/B = 1/6-1/8
1/B=8-6/48
1/B=2/48
1/B=1/24
B=24
Now we know time taken to complete work is 24 days. Since according to question A have already complete the 1/4 of the work, We have to find out time it will take for B to complete it.
Let's assume work to be done 24:
so Left Work = Total Work - Completed Work(i.e. 1/4 of 24 = 6)
Left Work. = 24 - 6
Left Work = 18
Since B take 24 days to complete work so 24/24 = 1
So B work rate is 1 per day, B will complete work in
Rate of Work * work remaining = Time
i.e. 1 * 18 = 18 days
So answer is Option D.) 18 days