A and b can together do a piece of work in 15 days.b alone can do it in 20 days .in how many days can a alone do it
Answers
Answered by
0
A's 1 day work +B's 1 day work = 1/15
So, A's 1 day work = 1/15 - 1/20
= 1/60
So, A can do the same work in 60 days
So, A's 1 day work = 1/15 - 1/20
= 1/60
So, A can do the same work in 60 days
Answered by
7
A and B → 15 days
A → 20days
So, let's take LCM of 15 and 20. That's 60.
This 60 unit is the total work to be done.
So, A and B do (60/15) = 4 unit work/day …(1)
And, A does (60/20) = 3 unit work/day …(2)
(1)-(2) gives
B does (4–3)= 1 unit/day
So, Total days req. = (Total work)/unit per day
i.e, B can do it in (60/1)=60 days.
A → 20days
So, let's take LCM of 15 and 20. That's 60.
This 60 unit is the total work to be done.
So, A and B do (60/15) = 4 unit work/day …(1)
And, A does (60/20) = 3 unit work/day …(2)
(1)-(2) gives
B does (4–3)= 1 unit/day
So, Total days req. = (Total work)/unit per day
i.e, B can do it in (60/1)=60 days.