A and b can together do a piece of work in 6 days and a alone can do it in 9 days. The number of days b will take to do it alone is

Answers

Answered by akhilesh622
0
use simply ratio and proportion to solve the given problem
Answered by debtwenty12pe7hvl
0

A+B, complete the work= 6 days

A+B one day work =1/6 part

A alone = 9 days

A one day work =1/9 part

let B complete the work= x days

A one day work =1/x part

∴ 1/9+1/x =1/6 part

⇒1/x =1/6 - 1/9

⇒1/x =1/18

x=18 days

B will take to do it alone in 18 days   ANS