A and B can together do a work in 10 days, B and C can do the same work in 12days , A and C can do the same work in 15days .how long each will take to do it seperately
Answers
Answered by
1
Answer:
(A+B) s, 1 day's work= 1/10
(B+C) s, 1 day's work= 1/12
(C+A) 1 day's work= 1/15
On adding,
2(A+B+C)
1 day's work= 1/10+1/12+1/15
6+5+4/60 = 1/4
∴(A+B+C) 1 day's work= 1/8
∴A 1 day's work= 1/8-1/12=3-2/24 = 1/24
∴A alone will complete the work in 24 days.