A and b can together finish a work in 30 days. They worked together for 20 days and then b left. After another 20 days, a finished the remaining work. In how many days a alone can finish the job?
a.40
b.50
Answers
Answered by
3
A and B can together finish a work in 30 days.they worked together for 20 days and then B left . After another 20 days , a finished the remaining work . in how many days A alone can finish the job ?
(A + B )'s 30 days work = 1/ 30 units
since they worked together for 20 days .then Find the work done by A and B in 20 days.
( A + B )'s 20 days' work = ( 1 × 20 )/ 30
= 20 / 30 = 2 / 3 units
Find the remaining work :
-----------------------------------
remaining work = 1 - ( 2/ 3) = 1 / 3 units
since , B left the work after 20 days , so it means that the remaining work is done byA alone. in given statement it is also mentioned that A finished the remaining work in 20 days.
since , remaining work = 1/ 3 units
1/3 units work is done by A in 20 days.
then,
whole work will be done by A in
( 20 × 3 ) = 60 days
therefore,
A alone can finish the job in 60 days .
Answer : 60 days (none of the above)
--------------------------------------------------------
(A + B )'s 30 days work = 1/ 30 units
since they worked together for 20 days .then Find the work done by A and B in 20 days.
( A + B )'s 20 days' work = ( 1 × 20 )/ 30
= 20 / 30 = 2 / 3 units
Find the remaining work :
-----------------------------------
remaining work = 1 - ( 2/ 3) = 1 / 3 units
since , B left the work after 20 days , so it means that the remaining work is done byA alone. in given statement it is also mentioned that A finished the remaining work in 20 days.
since , remaining work = 1/ 3 units
1/3 units work is done by A in 20 days.
then,
whole work will be done by A in
( 20 × 3 ) = 60 days
therefore,
A alone can finish the job in 60 days .
Answer : 60 days (none of the above)
--------------------------------------------------------
Answered by
6
Amount of work A and B do the work in 30 days
⇒ 1 day = 1/30 of the work
⇒ 20 days = 20 x 1/30 = 20/30 = 2/3 of the work
Find the remaining of the work:
Remaining of the work = 1 - 2/3 = 1/3
A can finish the remaining of the work in 20 days:
1/3 of the work = 20 days
3/3 of the work = 20 x 3 = 60 days
Answer: A can finish the work alone in 60 days