A and B can together finish a work in 40 days. They worked together for 20 days and then A left. After another 10 days, B finished the remaining work. In how many days B alone can finish the whole work?

Answers

Answered by dipti1138
1

Answer:

B needs 30 days more to finish the work

Answered by ramya320858
0

Answer:

20 days