A and B can work separately and can develop question in 12 and 15 days respectively if they work alter natively on the questions and a being question development then in how many days will the work be completed
Answers
Answered by
30
Step-by-step explanation:
alternatively (A+B)'s consecutive two day's work=1/12+1/15=3/20
after 12 days
3/20*6=18/20
work remaining 2/20
at 13th day 2/20-1/12=1/60(work remaining)
at 14th day 1/60*15=1/4
it takes 1/4 of 14th day
so total 13 and 1/4days
work completed in 12 days = (1/12 +1/15)*6 = 6*3/20 = 18/20 work = 9/10 work
work done by A on 13 th day = 1/12
work left after 13 days = 1- 9/10 -1/12 = 1/10-1/12 = 1/60
1/60 work will be completed by B on 14 th day by taking quarter of a day.
so total 13 1/4 days.