Math, asked by kakanisiva8593, 7 months ago

A and B complete a piece of work in 15 days and 10
days respectively. They contracted tocomplete the
work for Rs.30000. The share of A in the contracted
money will be​

Answers

Answered by pranjal318
2

Answer:

Rs.12,000

is the answer

Step-by-step explanation:

hope it helps you